Primus Residences Amenities

All the conveniences that complete modern-day living

Representational image#
Primus_01

External

Contemporary multi-storied development with 2 and 2.5-bedroom apartments, Landscaped greens on the ground, podium and terrace levels, for leisure and recreational facilities, IGBC Platinum pre-certification ,Grand entrance lobby and drop-off driveway, Rainwater harvesting-system and sewage treatment-plant, Multi-tier safety and security systems

No Amenities

Clubhouse

Rooftop gymnasium, a party hall and landscaped terrace , Ozonated and temperature-controlled swimming pool, kids' pool with deck, open-air Jacuzzi and splash pad, Spa with steam area and massage rooms, changing facilities and lockers, Indoor games room, Multi-function hall, and amphitheatre, Maze garden, Jogging/walking track, Fitness area, and climbing wall

Representational image#
primus_01
Representational image#
Primus_02
Representational image#
primus_03

Internal

Imported marble flooring, Engineered-wood flooring in master bedroom, Elegant veneered main door, and internal doors, Mobile-enabled smart home automation and provision for wi-fi, Gypsum-finished internal walls with low Volatile Organic Compound (VOC) acrylic paint, Synchronised light at main doors

Well-planned kitchen with provision for water purifier, Quartz-based agglomerated marble flooring, main and service platform, and dado, Stainless steel sink with drain board and food-waste disposer, TV point in kitchen, Kitchen equipped with CNG/LPG leak detector and heat/smoke detector, Exhaust fan, storage heater, and provision for water purifier in kitchen

Rain shower with body jet spray in master bathroom, Imported marble flooring and glass partitions in all bathrooms, Hot & Cold mixers in all bathroom wash basins, TV point in master bathroom, Designer tiled dado up to door height , Premium sanitary fixtures and CP fittings, Storage water heater and exhaust fans in bathrooms

Primus Residences Project Update

These are the latest images from the project-site. We look forward to the opportunity to take you through a live walk-through

Tower A (July 2019)
12th floor RCC Completed.
13th floor Column casting started.
Internal Plaster up to 6th completed.
External Plaster& internal brickwork up to 8th floor completed.

Tower B (July 2019)
RCC Completed.
Blockwork & Internal Plaster completed till 15th floor.
External plaster completed till 15th floor.

Tower B (July 2019)
Water proofing completed till 15th floor inside flats. Terrace W/P Completed.
Gypsum plaster completed till 15th floor.
Bathroom flooring/tilling & Room flooring completed till 15th floor.

Tower B (July 2019)
Internal painting up to 4th floor Completed.
Internal Plumbing up to 15th Completed.
Window work up to 15th completed.
Internal Painting 21 % completed.

Tower B (July 2019)
Metal work 100% completed.
External Plumbing in shaft 80% completed.
Fire Fighting inside the flat 97% & in shafts 47.36% completed.
Air conditioning line up to 89% completed.

Tower C (July 2019)
RCC Completed.
Blockwork & Internal Plaster completed till 15th floor.
External plaster completed till 15th floor.

Tower C (July 2019)
Water proofing completed till 15th floor inside flats.
Terrace W/P is in Completed.
Gypsum plaster completed till 15th floor.

Tower C (July 2019)
Bathroom flooring/tilling & Room flooring completed till 15th floor.
Internal painting up to 4th floor Completed.
Internal Plumbing up to 15th Completed.

Tower C (July 2019)
Window work up to 15th completed.
Door work completed.
Internal Painting 86.40% completed.

Tower C (July 2019)
Cp Sanitary Fitting 60% completed.
Finishing Entrance lobby 90 % completed.
Air conditioning inside the flat 100% completed .

External Development (July 2019)
Compound wall is completed.
Sewage Water drain work is completed.
RWH completed.
All chambers for HT and MTNL done.

External Development (July 2019)
PCC work is in progress.
Ramp Area Brickwork layout is completed.
Compound wall Painting & cladding work is in progress.

External Development (July 2019)
Ground level P CC Completed.
Arrival Experience work is in progress.
Landscape Soil Feeling in Planter Area Has been Completed.

External Development (July 2019)
Street lighting 10% work completed.
Solid waste management RWH 50% completed.
EMR Work 65 % completed.

External Development (July 2019)
Stack parking 25 % completed.
MEP Work 78% completed.
Compound wall 98 % completed.
BMS & CCTV work 45 % completed.

Entry Gate (July 2019)